Major earthworks

Major earthworks

The Major Earthworks contract was awarded to CPB Contractors and Lend Lease Joint Venture (CPBLL JV) in August 2019. On 9 September 2020 Acciona completed the acquisition of Lendlease Engineering and as such the Major Earthworks Contractor is now referred to as CPB Contractors and Acciona (CPBACC JV).

The major earthworks stage involves significant design and construction responsibilities, including moving around 25 million cubic metres of earth to support construction of the major elements of the airport, such as the runway and terminal.  

WSA and its contractors are committed to keeping the community and other stakeholders informed about the earthworks project as it progresses. We welcome your feedback on this project and our other activities. Please make contact with our community team (see contact details below).

 

Due to the NSW public health order relating to construction, activities on the project have ceased. 

You may notice security personnel around the site for the duration of the construction pause. 

The site, equipment and vehicles have been secured. 

For more information, please contact us at info@wsaco.com.au

 

What's happening?

July 2021

 

 

Notifications

Construction Notification 10 - May 2021 PDF: 794KB
Construction Notification 9 - December 2020 PDF: 328KB
Construction Notification 8 - OOH works October 2020 PDF: 257KB
Construction Notification 7 - October 2020 PDF: 341KB
Construction Notification 6 - September 2020 PDF:335KB
Construction Notification 5 - June 2020 PDF:288KB
Construction Notification 4 - May 2020 PDF:204 KB
Construction Notification 3 - March - April 2020 PDF: 250 KB
Construction Notification 2 - February 2020 PDF: 326 KB 
Construction Notification 1 - November 2019 PDF:3.01 MB

Community Updates

Community Update 3 - April 2021 PDF: 3.4 MB
Community Update 2 - December 2020 PDF: 7 MB
Community Update 1 - July 2020 PDF: 4.07 MB

Fact Sheets

Dust Mitigation Fact Sheet - PDF: 4.06 MB

 

Construction Work Hours

Standard work hours: 

•    Monday – Friday - 7am – 6pm 
•    Saturdays – 8am – 1pm 

Out of hours (OOH) work : We will consult and notify impacted residents prior to working outside of standard construction hours.

Contact

If you have any questions, or would like to provide feedback about the works, please contact the major earthworks’ team: 

  • Call 1800 972 972  
  • info@wsaco.com.au – General Enquiries  
  • wsabe.supply@cpblljv.com.au  - Procurement  
  • wsabe.employment@cpblljv.com.au – Employment