Register of building applications

WSA Consent # Applicant Date of Submission ABCO Reference Number Description WSA Co Determination WSA Co Determination Date ABC Determination ABC Determination Date
2018                
WSA18 - EEW - 01 Bechtel Infrastructure (Australia) Pty Ltd 30/08/2018 BAN-18-SWZ-0007 Construction of temporary haul road, temporary site compound and temporary stockpile area Approved 29/08/2018 Approved 13/09/2018
WSA18 - EEW - 02 Bechtel Infrastructure (Australia) Pty Ltd 19/09/2018 BAN-18-SWZ-0012 Stage 1 Clearing of Vegetation Approved 9/10/2018 Approved 11/10/2018
WSA18 - EEW - 03 Bechtel Infrastructure (Australia) Pty Ltd 18/10/2018 BAN-18-SWZ-0013 Early Earthworks - Asbestos decontamination in Stage 2, 3 and 4, vegetation clearing, Cut and fill earthworks, stockpiling of material Approved 26/11/2018 Approved 27/11/2018
WSA18 - VC- 01 Bechtel Infrastructure (Australia) Pty Ltd 18/10/2018 BAN-18-SWZ-0014 Visitors Centre Earthworks and Civil works Approved 19/11/2018 Approved 22/11/2018
WSA18 - EEW - 04 Bechtel Infrastructure (Australia) Pty Ltd 13/11/2018 BAN-18-SWZ-0016 Construction of Twin Bridges on Realigned Badgerys Creek Road Approved 6/12/2018 Approved 24/12/2018
2019                
Experience Centre             
WSA19 - VC01 Watpac Construction (NSW) Pty Ltd 9/01/2019 BAN-19-SWZ-002 Visitors Centre - Slab and Services Approved 10/01/2019 Approved 14/02/2019
WSA19 - VC02 Watpac Construction (NSW) Pty Ltd 31/01/2019 BAN-19-SWZ-002 Visitors Centre - Site Services Approved 4/02/2019 Approved 6/03/2019
WSA19 - VC03 Watpac Construction (NSW) Pty Ltd 24/04/2019 BAN-19-SWZ-002 Visitors Centre and Site Office Accommodation - Stage 3 Site Tanks and Pumps. Approved 29/04/2019 Approved 6/06/2019
WSA19 - VC02 Watpac Construction (NSW) Pty Ltd   BAN-19-SWZ-003 Visitors Centre Site Office Accommodation - Stage 3 Site Tanks and Pumps(Amended (No.3)  Approved 17/05/2019 Approved 6/06/2019
WSA19 - VC02 Watpac Construction (NSW) Pty Ltd   BAN-19-SWZ-003 Visitors Centre Site Office Accommodation - Stage 3 Site Tanks and Pumps(Amended (No.4)  Approved 28/05/2019 Approved 6/06/2019
WSA19 - VC04 Watpac Construction (NSW) Pty Ltd 1/05/2019 BAN-19-SWZ-002 Site Accomodation Structure (Stage 4) (Amended 6 May 2019) Approved 1/05/2019 Approved 7/05/2019
WSA19 - VC05 Watpac Construction (NSW) Pty Ltd 23/04/2019 BAN-19-SWZ-002 Landscaping works Approved 3/05/2019 Approved 3/07/2019
WSA19 - VC05 Watpac Construction (NSW) Pty Ltd 1/07/2019 BAN-19-SWZ-002 Landscaping works - amended Approved 11/07/2019 Approved 29/07/2019
WSA19 - VC06 Watpac Construction (NSW) Pty Ltd 20/05/2019 BAN-19-SWZ-002 Visitor Centre Fit-out Works  Approved 24/05/2019 Approved 24/05/2019
WSA19 – VC07 Bechtel Infrastructure (Australia) Pty Ltd 20/05/2019 BAN19-SWZ 0017 Substation 54081 for Visitor Centre & Associated Areas  Approved 24/05/2019 Approved 5/07/2019
WSA18 - VC01 Bechtel Infrastructure (Australia) Pty Ltd 19/05/2019 BAN-18-SWZ-0014 Visitors Centre Earthworks and Civil works  - Amended Approved 17/06/2019 Approved 18/06/2019
WSA19 - VC07 Watpac Construction (NSW) Pty Ltd 6/06/2019 BAN-19-SWZ-002 Site Office Accomodation Fit-out works - amended Approved 18/06/2019 Approved 19/06/2019
WSA19 - VC08 Watpac Construction (NSW) Pty Ltd 19/08/2019 BAN-19-SWZ-002 Site Office Accomodation Pergola Approved 21/08/2019 Approved 22/08/2019
WSA19 - VC09 Watpac Construction (NSW) Pty Ltd 22/08/2019 BAN-19-SWZ-0024  Visitor Centre Entry Sign and Security Camera Pole  Approved 27/08/2019 Approved 27/08/2019
              3/09/2019 4/09/2019
Early Earthworks                
WSA19 - EEW05 Bechtel Infrastructure (Australia) Pty Ltd 20/01/2019 BAN-19-SWZ-004 EEW Satellite Site Compound for pavements work for realigned Badgerys Creek Road Approved 12/02/2019 Approved 13/02/2019
WSA19 - EEW06 Bechtel Infrastructure (Australia) Pty Ltd 12/03/2019 BAN-19-SWZ-0012 Temporary Roundabout off existing Badgerys Ck Rd Approved 14/03/2019 Approved 27/03/2019
WSA19 - EEW07 Bechtel Infrastructure (Australia) Pty Ltd 7/03/2019 BAN-19-SWZ-0011 Demolition Authorisation for house, carport, septic tank, slab Approved 19/03/2019 Approved 20/03/2019
WSA19 - EEW08 Bechtel Infrastructure (Australia) Pty Ltd 24/03/2019 BAN-19-SWZ-008 Temporary Haul Road and Modified Stockpile Approved 28/03/2019 Approved 2/04/2019
WSA19 - EEW09 Bechtel Infrastructure (Australia) Pty Ltd 12/04/2019 BAN-19-SWZ-016 Removal of 67 Radiata Pine trees Approved 17/04/2019 Approved 17/04/2019
WSA19 - EEW10 Bechtel Infrastructure (Australia) Pty Ltd 11/04/2019 BAN-19-SWZ-004 Stage 2 - Pavement Works Package Approved 28/05/2019 Approved 29/05/2019
WSA19 - EEW11 Bechtel Infrastructure (Australia) Pty Ltd 20/06/2019 BAN-19-SWZ-0019 Basin 1 Construction - Stage 1 Vegetation Removal Works  Approved 25/06/2019 Approved 26/06/2019

WSA19 - EEW12

Bechtel Infrastructure (Australia) Pty Ltd

26/06/2019

BAN-19-SWZ-0015

Utilities Substation 53939

Approved

     
WSA19 - EEW13 Bechtel Infrastructure (Australia) Pty Ltd 23/02/2019 BAN-19-SWZ-0010 Airport Fencing Project - Stage 1 Approved 15/08/2019 Approved 16/08/2019
WSA19 - EEW13 Bechtel Infrastructure (Australia) Pty Ltd 24/02/2019 BAN-19-SWZ-0010 Airport Fencing Project - Stage 2 Approved 4/10/2019 Approved 4/10/2019
WSA19 - EEW14 Bechtel Infrastructure (Australia) Pty Ltd 15/08/2019 BAN 19 SWZ 0021 Temporary Diversion Road to the Existing Badgerys Creek Road To be withdrawn      
WSA19 - EEW15 Bechtel Infrastructure (Australia) Pty Ltd 5/09/2019 BAN 19 SWZ 0025 Potable Water Installation & Rectification Works Mersey Road & WSA Boundary Site  Approved 4/10/2019 Approved 4/10/2019
WSA19 - EEW16 Bechtel Infrastructure (Australia) Pty Ltd 27/09/2019(Not submitted to WSA)  BAN 19 SWZ 0026 Geotechnical Borehole Works(4), Adjacent to The Northern Road & Eaton Road Intersection     Approved 30/09/2019
WSA19 - EEW17 Bechtel Infrastructure (Australia) Pty Ltd 8/10/2019 BAN 19 SWZ 0027 Watermain Modification Works Jagelman Road & Fuller St at Badgerys Creek Road        
WSA19 - EEW18 Bechtel Infrastructure (Australia) Pty Ltd 4/10/2019 BAN 19 SWZ 0028 Bulk Earthworks Site Shed Installation & Associated Survey Works